Leeming header

Leeming SHS educational support centre alterations, additions and new works by RIVETT.

Rivett Construction was awarded the new additional administration area to match the existing building structures, consisting of connection to the existing structure, maintaining ongoing school operations.

Client

Department of Education

Category

Education

Design Team

MPS Architects

Project Value

$378,000.00

Duration

14 weeks (schedule 16 weeks)

Area

180sqm

Leeming SHS ECS Front View
Leeming SHS ECS Front View
leeming Internal inset2

Key challenges

  • Building within an operational school environment;
  • After-hours shutdown and changeovers to ensure continued amenity for the client;
  • Limit site access;
  • Tight Construction programme.

The project was completed within the original time allowance including a significant number of variation works for the school.

MPS Architects would have no hesitation in recommending Rivett Construction and would be happy to work with them in the future.

Julian Shaw MPS Architects