St MUNCHIN'S CATHOLIC PRIMARY SCHOOL Administration and ELC additions and alterations, Gosnells WA. Completed November 2016 on programme and budget. Thank you to Paterson Group Architects and the school staff for a great project.
Project
St Munchins Catholic Primary School
Project Value Commencement
$1,312,000.00 including GST
Project Value Completion
$1,328,000.00 including GST
Project Programme
26 weeks (to be completed 22 weeks)
Completion Date
November 2016


Client
Catholic Education
Architect
Paterson Group Architects
(08) 9485 2122
Greg Paterson - Principal
Key Challenges
-
Building within an operational school environment;
-
After-hours shutdown and changeovers to ensure continued amenity for the client;
-
Limited site access;
-
Tight Construction programme.


Key Building Features
-
Complete strip out, renovation and additions to the existing administration building to bring this building from 1970s standards to the present day requirements.
-
Demolition and expansion of the existing Early Learning teaching areas and facilities to meet present day standards and requirements.
-
Upgrading external car parking and drainage.
-
Removal and remedial works due to Asbestos contamination.