New Parent & Child Centre

Client               

Department of Education / Finance

Project

Arbor Grove PS Child & Parent Centre, Ellenbrook WA.

Value

 $1,365,285

Area

648sqm

Timeline

27 weeks (26 weeks completed)

Architect

Hodge Collard Preston Architects 

Project Summary

Rivett Construction was awarded the construction contract for the new Parent & Child Building at the Arbor Grove Primary School for the Dept of Education. The project was completed 1 weeks ahead of the construction programme.

Key Building Features
  • 348sqm Teaching Spaces, Offices & Staff facilities;

  • External Nature Play areas and landscaping;

  • High Standard details and materials;

  • New carpark and civil works;

Key Challenges 
  • Building within an operational school environment;

  • After-hours shutdown & changeovers to ensure continued amenity for the client;

  • Limited site access;

  • Tight construction programme.