Warwick Stadium Redevelopment

Client

COCSRWA 

Location

Hillarys, WA

Value

$8,700,000

Area

5300 sqm

Timeline

42 weeks (12 weeks early)

Completion

December 2015

Architect

Paterson Group Architects

Summary

Rivett Construction was awarded the construction contract for the Design & Construction of a large scale redevelopment of the existing 1980s sporting stadium increasing the floor plan by 5250sqm of indoor facility. This project was a culmination of 2 years design development with the design team and client to achieve the successful outcome and popular facility​

Key Building Features
  • 4 new sporting courts to FIBA international standards;

  • Changerooms & staff facilities;

  • 780sqm equipped Gymnasium

  • 500-seat Grandstand

  • New commercial kitchen & café;

  • New Entry, Foyers & Public spaces.​

Key Challenges 
  • Superior Stand of finish to reflect the original building and previous construction stages;

  • Building within an operational sporting environment with 24/7 timeframes and public use;

  • After-hours shutdown & changeovers to ensure continued amenity for the client; Limited site access;

  • Tight construction programme.

​